With the dryer weather now upon us, it was time to begin the construction of the Brookwood Extension.
After the initial removal of a 10610 straight section (1200mm) replaced with an electric left switch 16150, a straight section 10600 (600mm) and two straight sections 10080 (82mm), it was time to lay the foundations for the new bridge supports.
The first bridge support foundations were laid to a depth of 175mm using spar, sand and cement to a 3:2:1 ratio.
Once the foundations have dried, after approximately 7 days, two concrete edging stones will be mortared together and back filled with more concrete. (See future post.)
Whilst waiting for the conctrete to dry, I covered the whole area with a solid plastic sheet to help the mix to slowly dry and thus not crack. (Not illustrated.)