Brookwood - The Foundations (Stage 1a)















With two and a half rows of blocks laid, the station foundations are almost complete. At the bottom of the photograph another three blocks will be laid at the end of row two for the line to continue to the Ash Pit, Repair Pit and the Maintenance Shed.















The five dwarf conifers will be relocated once the foundations for the Maintenance Shed have been laid. It will be at this point that the building work for the foundations will stop and recommence most probably during Spring 2014 when the foundations for the line to the Engine Shed will be laid.















Looking along the line from where the platform will be, towards Brookwood Bridge which can be seen in the distance.

Tuesday, 9 April 2013

Cattle Van















Welshpool & Llanfair Light Railway type cattle van.

Model: Mainly constructed from injection moulded plastic, with 45mm wheel sets fitted.
Length: 285mm Accucraft UK-BMS: R19-22B
Scale: 16mm to 1 foot (1:19)

HLR Stock: 1

Monday, 8 April 2013

Brookwood - The Foundations (Stage 1)

As the weather continued to be kind I set about laying the first foundation stones for the line into Brookwood Station.
Unlike the rest of the line I decided to use 100mm grey solid dense blocks for the foundations to give a flat and wide area for gradually developing the station and it's sidings, block by block. The initial block was laid at the point where the line ended last summer.















Each block was laid on a mixture of soil and 6mm limestone after the ground had been thoroughly tampered down with a small concrete brick to help prevent movement in the future. Between each block a 12mm gap was left and a 4:1 mortar mix applied. 















Each block was carefully checked for level and after each was laid, the overall level was checked. Any surplus mortar was pointed alongside each stone at the foundations.















Bit by bit the the blocks were laid for the station platform line, all the way to where the buffer stop will be.















The initial blocks were left overnight before the track was loosely laid and engine tested. Now I think I'll leave it a week to settle before adding the next lot of adjacent blocks.

Tuesday, 2 April 2013

Brookwood - The Location

At last with the weather improving, I can begin to create Brookwood Village. During the winter months, of which there have been plenty, I have managed to collect plenty of track and building supplies ready for the contractors, builders, track gang and their fellow wayside workers to commence.















This is the site for the new village, just in front of the ruins of an old church. Two leveling pegs have already been positioned on the left and middle of the photograph. The current 'end of the line' can just be seen on the right of the photograph.

Friday, 8 February 2013

L&B Corridor Coach Kit Pt.3

The two pieces of each running board were next glued together and the window drop lights prepared.















A couple of coats of Humbrol Acrylic Gloss Varnish (35) were then applied and the parts left to dry prior to their fitting.

Tuesday, 5 February 2013

Brookwood - The Plan
















Based upon Llanfair Caereinion on the Welshpool & Llanfair Light Railway, this is what I have planned for Brookwood. There will be just one raised platform for passengers and a cattle and goods ramp behind the Engine Shed.

Track required

10000, G LGB 10000 Straight 300mm. 3
10090, G LGB 10090. Straight extendable 88mm-120mm. 1
10152, G LGB 10152 Straight separator 150mm. 1
10600, G LGB 10600 Straight 600mm. 13
10610, G LGB 10610 Straight 1200mm. 1
16000, G LGB 16000 Curve radius 1195mm, angle 22.5º(R3) 3
16050, G LGB 16050 Right turnout 440mm. 1
16150, G LGB 16150 Left turnout 440mm. 6
18000, G LGB 18000 Curve radius 2320mm, angle 15º(R5) 2

Wednesday, 30 January 2013

Box Car
















Model: The doors on both sides of the model slide open.
Length: 250mm LGB: 94007

Friday, 11 January 2013

L&B Corridor Coach Kit Pt.2.2

















Not my best paint job but not bad for what I am trying to achieve. With the newspaper and masking tape removed the seats were prepared and positioned into the coach.


Monday, 7 January 2013

Wednesday, 2 January 2013

Tanker Wagon Kit - Pt.2















The tank keeps were next located onto the chassis to sit flush with the ends of the anti-slip plate. The tank was in position whilst the glue set and two parallel were drawn on the tank ends on either side of the tank keeps. Later, between these lines, masking tape will be fixed prior to painting.

The tank keep bolts were drilled at an angle to accommodate the wire for the tie bars which were subsequently super glued to each bottom keep.

A small hole was next drilled into each coupling block. A coupling wire for each end was then bent into shape and glued into the prepared holes.















The completed tanker now waits to go into the body shop to be painted.